The 970 foot Keystone viaduct near Meyerdsale (Mile 29.5) has a small ramp where the viaduct merges with the truss bridge that passes over the CSX railroad. Most people pass over the small incline of the ramp and don’t think twice about the change in height. But if you think about it, a railroad will not have a ramp like this on their mainline track. It must be an indication of something else that happened.

That something else is that the CSX railroad raised the 128,000 ton truss bridge roughly two feet in order that its double stacked container cars can fit underneath the bridge. The ramp is the most obvious indicator of the bridge raising. The photo tour of the bridge raising provides you with numerous clues and evidence of the bridge raising.

Take a peddling break on the viaduct. Enjoy the view. Perhaps you can watch a train grinding its way up the steep grade. Take a little time and check for yourself the evidence of the bridge raising. It is the game of clues.

A Future Ramp. There was no information provided. One day someone partitioned off the east section of viaduct. Note the roadway is level onto the truss bridge. [Keystone Viaduct, 2011, GAP trail]
Constructing the Ramp. Half of the ramp is constructed so that when the truss bridge is raised, it will be level with the top of the ramp. [Keystone Viaduct, 2011, GAP trail]
Constructing the Ramp. This slide shows the original roadway next to the constructed ramp. The ramp on the west entrance to the truss bridge is gradual, and when completed, the ramp will not be obvious. [Keystone Viaduct, 2011, GAP trail]
Hydraulic Jacks. I-beam extensions were bolted onto the corners of the bridge and hydraulic jacks were placed under the I-beams. Although it is hard to see in this photo, the rivets were removed and bolts connected the I-beam extensions to the bridge. If you look carefully today, the bolts are present and indicate where the extensions were attached. [Keystone Viaduct, 2011, GAP trail]
The Night of the Keystone Viaduct Raising in 2011. [Keystone Viaduct, 2011, GAP trail]
Bridge Closed. The GAP trails is closed the night of the bridge raising. Note: I used the light on my bike to illuminate the “Bridge Closed” sign. [Keystone Viaduct, 2011, GAP trail]
Extending the Footers. Once the bridge is raised, the footers supporting the four corners of the bridge are filled in with concrete. [Keystone Viaduct, 2011, GAP trail]
Touch-Up Work. They did some touch-up underneath the raised footer. The new concrete has aged with time, but the difference in coloration is an indication of a raised bridge. [Keystone Viaduct, 2011, GAP trail]
The Ramp Today. The most obvious evidence today is the ramp in the background. Carefully, look at the railing. Its angle indicates the change in elevation and the bridge raising. You know where to look for additional clues of the bridge raising. [Keystone Viaduct, 2011, GAP trail]